During the construction of the Brașov main sewerage line, the excavation was carried out with a shield underneath the railway and led to an underground void with a diameter approximately 20cm larger than the outer diameter of the sewer made of prefabricated concrete elements.
To avoid settlements, the gap was filled with injection material in the Geopur® system.
During the execution of the injection works, specific topographic monitoring works were carried out for possible settlements of the railway lines. No settlements were found and as a result the railway traffic was not disturbed.

image gallery:

During the construction of the Brașov main sewerage line, the excavation was carried out with a shield underneath the railway and led to an underground void with a diameter approximately 20cm larger than the outer diameter of the sewer made of prefabricated concrete elements.
To avoid settlements, the gap was filled with injection material in the Geopur® system.
During the execution of the injection works, specific topographic monitoring works were carried out for possible settlements of the railway lines. No settlements were found and as a result the railway traffic was not disturbed.

image gallery:

Scroll to Top
Tehnologii de injectare cu rasini
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.